Aluminium Bungalows
To date, External Wall Insulation works schemes have been completed to aluminium bungalows in the following areas:
A further scheme in the Derry/ Londonderry area is currently in the procurement stage. This scheme will be 100% funded by NIHE.
No Fines Works, Tranche 1
Out of the 12 schemes in Tranche 1 to date, 10 schemes have been completed.
The remaining 2 schemes were partially completed by the originally appointed Contractor but are now scheduled to be completed by Response Maintenance Contractors or NIHE’s Direct Labour Organisation.
The completed improvement schemes include:
The schemes currently scheduled to be completed cover improvements in the following areas:
No Fines works, Tranche 2
To date 4 schemes have been completed with 7 schemes currently on site.
The completed improvement schemes include:
The schemes currently on site are in the following areas:
The 2 schemes below were partially completed by the originally appointed Contractor but are now scheduled to be completed by the NIHE’s Direct Labour Organisation or through a new Procurement:
No Fines works, Tranche 3
Three contracts have been awarded in August 2022 to complete works to approximately 450 properties with an estimated value of over £14million.
Elements of this tranche will be funded by 100% investment from the Northern Ireland Housing Executive.
The areas were this work will be undertaken are;